Our Role
ByrneLooby was commissioned by Arcadis (the designer) to undertake the Environmental Impact Assessment (EIA) including an Environmental Scoping Report (ESR), an Environmental Evaluation Report (EER), and Construction Environmental Management Plan (CEMP) in an extremely culturally and environmentally sensitive area in Arad Bay.
As part of the EER, ByrneLooby conducted various baseline studies including marine ecological surveys, water quality studies, noise monitoring, landscape and visual impact studies, culture and heritage impact assessment, air quality monitoring, as well as 3D hydrodynamic flushing modelling.
Based on the studies and environmental legislation and guidelines, ByrneLooby developed an EER and EMP to assess the potential impacts of the proposed STP an suggest mitigation measures and best practices to minimize the effect of any negative impacts.