Qatar

Lusail Energy City

detailed design work was key for this project's success

ByrneLooby carried out the detailed design of a temporary steel bridge over a deep excavation in the new Lusail Energy City. The 22m bridge was required to span a deep temporary vertical cutting which was 15m deep.

We delivered a bespoke buildable design which was developed to ensure that all materials required to construct the bridge were available locally.

Our design which incorporated standard steel sections and pile foundations at the abutments ensured our client has a robust cost effective bridging solution.

Scope of Project

  • Design of a temporary steel bridge with a span of 22m over a 15m deep excavation.
  • Value engineered design to ensure all materials required to construct the bridge were available in the region.
  • Design took account of sensitive services in close proximity to the bridge abutments.  